Lin Yiping went on to say: "The composition of the cost unit price of the sand and gravel cushion: the purchase price of the virtual square of the car side is 45 yuan per cubic meter. After checking the Nanhai quota, the virtual square of 1.26 cubic meters can be compacted into 1 cubic meter, which can be compacted after conversion. Fang’s material cost is 56.7 yuan per cubic meter; the cost of mechanical paving, rolling, manual coordination and other auxiliary materials is calculated at 30 yuan per cubic meter, and after considering business tax and surcharges, the cost unit price is 89.56 yuan per cubic meter.”

Bai Qingting asked: "The purchase price of the car side is 45 yuan per cubic meter. Has this price been consolidated?"

Lin Yiping replied: "In the process of consolidation, this price is temporarily adopted at a 5% drop from the local information price."

Bai Qingting asked: "Why hasn't the price of a floor material been implemented for so many days? Is this efficiency too low? Mr. Song?"

Song Zhiyuan replied with an unpleasant expression: "This is an arrangement, but there are currently three projects in operation in the Nanhai area, but only the Nanshan project has one material procurement, and the lack of complete staffing is one reason, and now the Nanshan project is under rush There are many things to do in the procurement of labor and materials, and it is also a reason that the procurement of materials cannot be dispatched in time for inquiry.”

Bai Qingting slapped the table and said angrily, "Don't give me a reason. If there are not enough people, we will recruit people. This project is so important, how can no one ask for quotations? Mr. Song, you have to find a way to solve this problem. There can be these problems again.”

Song Zhiyuan smiled bitterly and said, "Mr. Bai, after the meeting, the people in our business department will carefully plan and solve these related problems seriously and practically. You can rest assured."

Bai Qingting replied: "Okay, everyone's work must be done with snacks, don't take this as the company's business, and do the company's business as your own.

Xiaolin, you go on to the next one. "

According to Bai Qingting's request, Lin Yiping continued to report: "C15 concrete cushion cost unit price: C15 concrete material cost is 180 yuan per cubic meter, and labor and machinery costs such as pouring, vibrating, and maintenance are considered at 30 yuan per cubic meter. The cost is 210 yuan, plus business tax and additional costs, the unit price is 216.93 yuan per cubic meter."

Bai Qingting asked, "Have you considered the loss of concrete?"

Lin Yiping replied: "The loss of concrete is not large, and I have not considered its loss coefficient in the cost. The cost unit price of the concrete foundation, concrete wall, concrete slab, etc. is also calculated in this way, but there is a small difference in the unit price of the labor service. , is it possible to stop reporting these concrete items?"

Bai Qingting replied: "Yes, and then report other cost unit prices."

Lin Yiping continued to report: "For the production and installation of steel bars, let's start with the diameter of round steel within 10mm. The labor fee is calculated at 1,100 yuan per ton, the material cost is calculated at 4,000 yuan per ton, and the unit cost is 5,268.3 yuan per ton."

Bai Qingting said: "Is the labor fee of 1,100 yuan too high? What is the fixed fee in Nanhai?"

Zhang Yunqing replied: "Mr. Bai, the common cost for the production and installation of steel bars is 800-1,200 yuan per ton. According to the amount of steel, the unit price of labor services will fluctuate. The fixed cost of Nanhai is 1,215 yuan per ton."

Bai Qingting asked Lin Yiping: "Xiao Lin, the manager of the Nanhai area said that the steel service fee range is 800-1,200 yuan per ton. You are currently using the cost of 1,100 yuan per ton. Why not use the lower limit of 800 yuan per ton?"

Lin Yiping replied: "Mr. Bai, the steel bars with a diameter of less than 10mm in our first bid section are only a few tons on the bidding list, so I chose a higher cost unit price. If I choose 800 yuan per ton, the labor service team will It's going to be a loss."

Bai Qingting continued to ask: "Has the material cost of your steel bars considered the loss?"

Lin Yiping replied: "I didn't consider the loss, what I think is that his steel bars are a little thinner, and less waste in the production process should be able to overcome this problem.

Next, I will report the unit price for the production and installation of rebar with a diameter of 10mm or more and less than 25mm. The labor fee is calculated at 980 yuan per piece, the material is calculated at 3950 yuan per ton, and the cost unit price is 5092.69 yuan per ton.

The cost unit price of the steel formwork is from the inquiry. It is calculated according to the cost of the labor service team after renting the steel formwork. There is not much to explain, so I will report the price directly. The cushion steel formwork is 26 yuan per square meter, the basic steel formwork is 35 yuan per square meter, and the column, beam, slab and wall steel formwork is 60 yuan per square meter. "

Bai Qingting asked: "How much profit margin does the cost unit price of the template leave for the next family?"

Lin Yiping replied: "According to what we know, only the management fee of the labor service team is left, and the profit is 1% or 2%."

Bai Qingting replied: "The profit of the labor service team is too low, will they give us a good job? President Song?"

Song Zhiyuan replied: "Mr. Bai, this is only a theoretical profit calculation. In reality, there are many influencing factors in the construction process. If we increase the theoretical profit for the labor service team, our company will pursue There is no way to guarantee the high profit of the labor force. I think as long as the labor team is still willing to do our work, he should have his due profit in it. We do not need to investigate this data too carefully~www.readwn.com~ After all A large part of the profit of the project comes from good management of the site.”

Bai Qingting replied: "Everyone should pay attention to the profit of this labor service team. We have more and more projects now, and we can't do without the support and help of these old teams. Don't let them feel sad and chilled."

Song Zhiyuan nodded slightly to express his respect for Bai Qingting's arrangement.

Bai Qingting turned her head towards Lin Yiping and said, "Xiao Lin, you continue to report the cost unit price."

Lin Yiping continued to report: "The unit price of brick foundation: 525 standard bricks are used per cubic meter of brick foundation, the purchase price of each brick is 0.3 yuan, the material cost of brick is 157.5 yuan per cubic meter, and the material cost of mortar is about 0.3 cubic meter. It is 72 yuan, the manual masonry cost is 200 yuan per cubic meter, and the unit price after considering business tax and surcharges is 443.67 yuan per cubic meter."

Bai Qingting asked, "Has the loss of bricks been considered? Has the loss of mortar been considered?"

Lin Yiping replied: "The loss of these two materials is not considered. The brick wall is similar to the brick foundation, but the labor cost is 20 yuan per cubic meter higher, so it will not be analyzed separately.

The cost unit price of 20mm thick M5 cement mortar wall plastering is reported below:

First, the wall cleaning is 0.5 yuan per square meter, and then the cement slurry wet primer is 0.8 yuan per square meter. The material cost of the first plastering 13mm is considered as 11 yuan per square meter, and the second plastering 7mm is 9 yuan per square meter. The unit price is 22 yuan per square meter, plus business tax and additional costs. "

Bai Qingting asked, "Is the unit price of your plastering a little less than the cost?"

Lin Yiping replied, "Mr. Bai, it's all done, no less?"

Bai Qingting asked: "The plastering usually requires scaffolding to be plastered. What about the cost of the scaffolding?"